I have servers in a merge scenario that replicate every ten minutes. When
changes occur, they need to replicate fairly quickly (within 30 minutes),
but changes may not occur in every hour.
I think it would be most efficient to run continuous rather than every 10
minutes. However, I would really like replication to not be running at all
outside of the 8am-5pm window. Is it possible to have continuous
replication, but only from 8am to 5pm? The SQL Enterprise Manager does not
seem to allow for it.
Rob Kraft
Sure. Add a job that runs at 8AM and again at 5PM. What does this job do?
It changes the schedule on the replication job.
Mike
Principal Mentor
Solid Quality Learning
"More than just Training"
SQL Server MVP
http://www.solidqualitylearning.com
http://www.mssqlserver.com